Arlington has selected a contractor for a new roundabout at Smokey Point Boulevard and 180th Street NE, moving the project another step toward construction.
The City Council on Nov. 16 approved a $3,456,789.10 award to Reece Construction Company and authorized the mayor to sign the construction contract, pending final approval by the Washington State Department of Transportation. The approval appears at 42:12 through 42:48 in the city’s meeting recording.
What the project includes
The city’s bid notice describes a single-lane roundabout, sidewalks, lighting and pedestrian crossing beacons, along with stormwater, water and sewer work.
The construction award is one part of the cost. The council’s award report lists a $4.94 million project budget for 2027, including land acquisition and construction management. It identifies about $3.65 million in grant funding and $1.29 million from city transportation funds.
Staff said the project was carried forward from the 2026 budget because of a delay in putting it out to bid. The Nov. 16 award materials do not provide a confirmed construction start date or a traffic-detour schedule.
A separate decision on land
The council also approved an amendment allowing the city to acquire an entire parcel at 17930 Smokey Point Boulevard, rather than part of it, for the roundabout.
City Attorney Oskar Rey told councilmembers that discussions with the property owners’ attorney led to the change because of the project’s effects on the land that would otherwise remain. He described a tentative agreement and said a purchase-and-sale agreement would follow. The staff report lists a $715,000 purchase price.
The ordinance changes the scope of the city’s acquisition authority. It does not establish that the purchase has closed. Rey’s explanation and the council’s vote appear at 44:56 through 46:49 in the meeting recording.
Drivers can check the city’s roundabout project page for future construction and access notices.